曹新明,王建珍.北京市阳光广场降水与锚拉护坡桩工程施工设计及工艺[J].地质与勘探,1995,(2):51-54 |
北京市阳光广场降水与锚拉护坡桩工程施工设计及工艺 |
Construstion Design and Technology of Drawdown and Anchored Slope Proteotion Pile Eegineering in Sunlight Plaza of Beijing City |
|
DOI: |
中文关键词: 降水 锚拉 护坡桩 深基础 工程施工 |
英文关键词: deep foundation pit and large area,drawdown and anchored slope protection pile |
基金项目: |
曹新明 王建珍 |
冶金部第一地质勘察基础工程公司 |
摘要点击次数: 2035 |
全文下载次数: 1199 |
中文摘要: |
阐述了深基坑大面积基础工程的降水与护坡的设计原理,成井灌注桩施工工艺及实际应用效果,为深基坑大面积降水和锚拉护坡桩工程的进行提供了参考依据。 |
英文摘要: |
n deep foundation pit and large area foundation engineering,the design principle of drawdown and anchored slope protec-tion,the working technology of well completion poured pile and its applications are presented, which is of reference value to en-gaging in the deep ground pit and large area drawdown and anchored slope protection engineering. |